About the repair works performed at the 330 sq.m

In agreement with the National Dispatch Center, 330 kV substation “Gardabani” was put into repair on September 03 and 04, 2020, in order to carry out operational and repair works on the power transmission line.

According to the agreed calendar plan-schedule, 330 sq.m. “Gardabani” was to be repaired for 6 days – from September 1 to September 6 inclusive.Due to certain reasons, the so-called “Gardabani” was under repair for 19 days at different times of the current year, during which time the staff of JSC GE “Sakrusenergo” performed certain volumes of repair work provided for in the plan, due to which it was enough to put it in repair for two days to complete the work.

In 2020, while the 330 sq.m. “conversion” was under repair, the following were completed:

NN 23; 24; 26; 27; 30; 32; 33; 34; 35; 36; 43; 56; 57; 59; 60 removal of bird nests from mast traverses;
Replacement of insulators bent in the stalk on N40 and N45 masts, a total of 8 insulators;
Elevation view of EKG – 17 masts;
NN41-42 cutting of sprouting plants in Mal and others.

The works were carried out by the personnel of Tbilisi operation-repair area and transport service.

Other news

ლოგო-1-1200x857-2-qw31cbgkq2fy8i4erku8k3du5unuj5rgxx5ldl8rds

სს გეს „საქრუსენერგო“-ს აქციონერთა საერთო კრების შესახებ

ლოგო-1-1200x857-2-qw31cbgkq2fy8i4erku8k3du5unuj5rgxx5ldl8rds

სს გეს „საქრუსენერგო“-ს აქციონერთა საერთო კრების შესახებ

ლოგო-1-1200x857-2-qw31cbgkq2fy8i4erku8k3du5unuj5rgxx5ldl8rds

General Meeting of shareholders of JSC UES SAKRUSENERGO

This site is under construction