In August-September 2011, S.S. A brief overview of the works performed on the power transmission lines of “Sakrusenergo”.
E.G.Kh. “Caucasus”
Deforestation works were carried out in the sections between towers No. 28÷48, No. 97÷100, No. 137÷147 in the areas adjacent to Jvari, S. Idliani, S. Lakham and Khidal. Deforestation works were also carried out in the Russian section, namely: №32÷38, №141÷160, №579÷607 in Mali on the territories of Karachaevo, Zelenchuk, Afsheron and Maikof;
Broken insulators were replaced on masts #139, #142, #147, #148, #149, #150 in the Georgian section, and on #2, #10, #16, #715 masts in the Russian section;
E.G.Kh. “Imereti”
In the first half of August, the felling works started in July in №98÷262 were finished, and in the first half of September, the felling works started in August in №19÷98 were finished; The project was completed and according to the project, the works of moving the 295 У2+5 type mast from the landslide zone were carried out; In order to increase the gauge of the wires near the ground, the ground was cut with a bulldozer #60-61, #66-67, #105-106 and #115-116 in Mal;
Repair works were carried out in seven malls of the line, in particular, switches #46-47, #57-58, #64÷67, #92-93, #98-99, #355-356, #370-371 were installed in malls;
In the month of October, large-scale deforestation works are planned and currently underway in Mali #262÷389;
E.G.Kh. “Kartli-2”
Deforestation works No. 177÷180, No. 182-183, No. 185÷189, No. 193-194, No. 200-201, No. 206÷214, No. 215-216, No. 378÷381, No. 382÷384 were performed in Mali;
E.G.Kh. “threat”
The painting works of the metal constructions of the towers on section #1÷36/1 were finished; A large part of the planned repair work was carried out on the section between masts No. 42÷280, namely: the foundations were repaired, the angles removed for the purpose of robbery were installed, the mast-supporting beams were tightened, the displaced garlands were straightened on thirty supports, felling works No. 172, No. 179, No. 181, No. 182 were performed. , #186, #188, #236-237, #240÷243, #245÷250, #252-253, #257-258, #259÷265A in the bars and mast bases;
The repair works of E.G.Kh continue on the section between the towers #42÷#280; The estimated date of completion of the planned repair and forest cutting works is October 2011;
E.G.Kh. “Adjara”
Deforestation works No. 1÷5, No. 7-8 in Mal were completed;
For the construction of the access road from tower #44 to tower #49 of E.G.K.
section.