In October 2011, S.S. A brief overview of the works performed on the power transmission lines of “Sakrusenergo”.
E.G.Kh. “Caucasus”
Deforestation works were carried out in the section between towers #89÷97 in the area adjacent to the village of Idliani. Deforestation works were carried out in the Russian section as well, namely: #27÷28, #29÷31, #599÷601, 604÷605, 751÷753 in Mali on the territories of Karachaevo, Apsheron and Maikof districts;
Broken insulators were replaced on masts #61 and #63 in the Georgian section, and on masts #17, #21, #30, #44 and #121 in the Russian section;
E.G.Kh. “Imereti”
In the month of October, the large-scale logging works started in September on the section between the masts #262÷389 were completed, thus the logging of the entire length of the “Imereti” was completed.
E.G.Kh. “Kartli-2”
The landslide-prone area around mast #194 was inspected together with geologists, in order to prepare an engineering-geological conclusion-recommendation and to make an appropriate decision.
E.G.Kh. “threat”
– During the mentioned period, the foundations were laid in the section №1÷36/1 and a new Р2 type mast №13 was installed. The foundations for the installation of the new У2 type No. 24 A mast, which is scheduled to be installed at the beginning of November, have also been laid.
– In the month of October, the planned works on the section between towers #42÷280 of the “Mukhrani” were completed. In particular, the following types of work were performed: broken and contaminated insulators were replaced, protective gvarli relief horns were installed, angles removed as a result of robbery were restored, anti-robbery measures were also carried out, damaged bypass loops were repaired, displaced garlands were straightened on 51 masts, internal connections were adjusted on reinforced concrete masts. , earth cutting works were carried out in order to increase the gauge in malls No. 150-151 and No. 159-160.
– Deforestation works No. 44-45, 50-51, 70-71, 74-75, 79-80, 139-140, 140-141, 149-150, 163-164, 169-171, 173-174, 177 were carried out. -178, 179-187, 214-215, 217-218 in Malls, which ended the cutting of the entire length of the Egkh.
– Installation of a new У2 type mast #24A and cable installation works are planned in section #1÷36/1 in November.