In October 2011, S.S. A brief overview of the works performed on the power transmission lines of “Sakrusenergo”.

In October 2011, S.S. A brief overview of the works performed on the power transmission lines of “Sakrusenergo”.

E.G.Kh. “Caucasus”
Deforestation works were carried out in the section between towers #89÷97 in the area adjacent to the village of Idliani. Deforestation works were carried out in the Russian section as well, namely: #27÷28, #29÷31, #599÷601, 604÷605, 751÷753 in Mali on the territories of Karachaevo, Apsheron and Maikof districts;
Broken insulators were replaced on masts #61 and #63 in the Georgian section, and on masts #17, #21, #30, #44 and #121 in the Russian section;

E.G.Kh. “Imereti”
In the month of October, the large-scale logging works started in September on the section between the masts #262÷389 were completed, thus the logging of the entire length of the “Imereti” was completed.

E.G.Kh. “Kartli-2”
The landslide-prone area around mast #194 was inspected together with geologists, in order to prepare an engineering-geological conclusion-recommendation and to make an appropriate decision.

E.G.Kh. “threat”
– During the mentioned period, the foundations were laid in the section №1÷36/1 and a new Р2 type mast №13 was installed. The foundations for the installation of the new У2 type No. 24 A mast, which is scheduled to be installed at the beginning of November, have also been laid.
– In the month of October, the planned works on the section between towers #42÷280 of the “Mukhrani” were completed. In particular, the following types of work were performed: broken and contaminated insulators were replaced, protective gvarli relief horns were installed, angles removed as a result of robbery were restored, anti-robbery measures were also carried out, damaged bypass loops were repaired, displaced garlands were straightened on 51 masts, internal connections were adjusted on reinforced concrete masts. , earth cutting works were carried out in order to increase the gauge in malls No. 150-151 and No. 159-160.
– Deforestation works No. 44-45, 50-51, 70-71, 74-75, 79-80, 139-140, 140-141, 149-150, 163-164, 169-171, 173-174, 177 were carried out. -178, 179-187, 214-215, 217-218 in Malls, which ended the cutting of the entire length of the Egkh.
– Installation of a new У2 type mast #24A and cable installation works are planned in section #1÷36/1 in November.

Other news

ლოგო-1-1200x857-2-qw31cbgkq2fy8i4erku8k3du5unuj5rgxx5ldl8rds

According to the decision made by the Supervisory Board of JSC UES SAKRUSENERGO on April 21, 2025 (Protocol No. 5), Mamuka Menagharishvili has been appointed as the General Director of the company

ლოგო-1-1200x857-2-qw31cbgkq2fy8i4erku8k3du5unuj5rgxx5ldl8rds

სს გეს ,,საქრუსენერგოს”-ს აქციონერთა საერთო კრების შესახებ

ლოგო-1-1200x857-2-qw31cbgkq2fy8i4erku8k3du5unuj5rgxx5ldl8rds

An extraordinary General Meeting of Shareholders of JSC UES SakRusenergo is scheduled for December 27, 2024 at the address Georgia, Tbilisi, Mark Bronstein Street No. 1 at 15:00 local time, with the following agenda

This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.