A brief overview of works performed on power transmission lines of JSC “Sakrusenergo” in December 2012
E.G.Kh. “Caucasus”
In the section of Georgia, masts No. 24, 29, 95, 96, which were robbed of their angles, were restored, in total 263 meters of angles were installed.
Deforestation works were carried out in the Russian section, in particular, the trees of Egkh No. 171-173, 451-453, 468-470, 711-722 were felled.
(17 Mali – 5 km). The access road to mast No. 713 was excavated and cleaned. No. 217, No. 234, No. 388, No. 397, No. 496a were inspected in landslide-prone zones.
Masts No. 711, No. 712, No. 713. A planned bypass of the EGK was carried out in the sections between towers #9-287 and #687-756 (143.8 km).
The short-term point of ice sheet melting was observed.
E.G.Kh. “Imereti”
The following types of works were carried out during the 1-day repair period of the EKH: broken insulators were replaced
on masts No. 80, 118, 120, 389, 390, 48 pieces in total; The damaged wires of the loop were replaced on phase B of mast #310.
In order to increase the gauge, the land in mall No. 173-174 was cut with a bulldozer. It was restored from the angular ones
Masts No. 226, 229, 230 were robbed, a total of 123 meters of angular was installed.
E.G.Kh. “Kartli-2”
No. 250, 264, 270, 271, 272, 277, 302, 314, 315, 328, 332, 375, 379, 384, 385, 388, 389 intermediate
legs of masts. Corrected the landslide that occurred in mall No. 317-318.
E.G.Kh. “Kartli-1”
Defective anchor bolts were installed on masts No. 1, 2 and 3.
E.G.Kh. “threat”
The relief horns were straightened on the protective gvarl of the towers #42, 43, 45, 48, 49, 50, 51, 52, 53, 54, 55, 59. It was installed on mast #42
Defective vibration dampener, on masts No. 43 and 58, the clamps were adjusted, on mast No. 47, anchor wrenches were tightened,
Internal connections were adjusted on mast No. 51, clamps were installed on masts No. 57, 58.
The deviated reinforced concrete mast of type №80 ПБ-500-5Н was straightened.
The works of hanging the third wire in the section between masts No. 42-No. 59, which started last month, have been completed.