A brief overview of the works performed on the power transmission lines of JSC “Sakrusenergo” in September 2013

E.G.Kh. “Caucasus”
In the section of Georgia, no repair and felling works were carried out in the month of September.
Cleaning works from plants were carried out in the Russian section, in particular, in areas #5-6, 6-7, 11-12, 12-13, 14-15, 15-16, 89-90, 124-125, 501-502, 512- 513, 514-514, 514-515, 544-545, 691-692, 692-693 in Mali. Towers #217, 234, 388, 397, 496а, 608, 609, 643, 644, 711, 712, 713 located in landslide prone zones were inspected. A tour of the section between the towers #5-48 of E.G.K. was carried out. “Imereti”
The #98 and #100 corner masts that were robbed from the anglers were recovered. Access roads to towers #244, 245, 246, 247, 248, 249, 250, 251, 252, 253, 254 were restored by bulldozer. The bases of masts #389 and #390 were cleaned from thorns.

E.G.Kh. “Kartli-2”
From September 10th to September 17th, during the 8-day overhaul of the EGK, the following repairs were performed: Replaced porcelain insulators with glass insulators on masts #77, 79, 82, 83, 105, 106, 369, 370, 386, 387, total of 10 corner 3870 insulators were replaced on the mast. Replaced broken insulators on masts #188-2c, #189-3c, #201-2c, #202-2c, #209-4c, #216-2c, #223-3c, #228-3c, #235-4c, # 236-2 pcs, #386-1 pcs, #407-2 pcs, #418-2 pcs, in total 32 insulators were changed on 13 masts. Replaced worn stubs on masts #407 and #418. In #386-387 Mall (highway crossing), 36 pieces of rectifier were replaced in all three phases, and triangles were attached to the ends of the garland on #386 and #387 masts with adjusting rings. In #81-82, 105-106 and 433-434 malls, damaged transformers were replaced, in total 34 transformers were installed in 3 malls. Damaged wire was repaired by placing artakh in #186-187 and #214-215 malls. In the A phase of #192-193 malls and in the C phase of #229-233 malls, a protective guard was installed. Trees and plants around masts #216, 217, 218, 219, 220, 438, 439, 445 were uprooted, and tall trees were cut in the side gauge of #330-331. #214-215 trees cut and temporarily stacked in the month of August were handed over to the forestry department. The painting works of the masts of section #369÷409 continued. “Kartli-1”
On September 3, during the 1-day repair of the power plant, broken insulators were replaced on masts #171 _ 5, #172 _ 1, #173-2, and protective gvarli vibration dampers were installed on the same masts. The throttle connected to #168 mast wires was canceled and the corresponding phase was moved to the loop.E.G.Kh. “threat”
#121, 122, 129 masts have been painted restored angular.

E.G.Kh. “Adjara”
A tour of the entire length of the railway station (#1-50) was conducted. #2, 14, 16, 21, 25 mast bases and surrounding area were cleaned and sanded.

Other news

ლოგო-1-1200x857-2

სს გეს ,,საქრუსენერგოს”-ს აქციონერთა საერთო კრების შესახებ

ლოგო-1-1200x857-2-1

On October 25, 2024, the next general meeting of shareholders of JSC “Sakrusenergo” was scheduled at 15:00 local time, Mark Bronstein St., Tbilisi, Georgia. No. 1 on the next agenda.

459312770_1124067569256084_6439192859944532317_n

საქართველოს ენერგეტიკოსის დღე

This site is registered on wpml.org as a development site. Switch to a production site key to remove this banner.