In coordination with the National Dispatch center of Georgia, transmission line Kavkasioni (500kV) will be under repair from August 5 to 31, 2023.

Repair-maintenance work will be performed on the line in accordance with the business plan 2023 of JSC UES SAKRUSENERGO. The repair process includes the following work: the replacement of the damaged and broken insulators, line accessories, repair of conductors, installment of the defective crossbars, discharger horns and vibration dampers. Trees and plants will be cut under the transmission line and within the protection zone. The employees of the contractor company will perform repair and plants removal work in the sections of the transmission line Kavkasioni in Gali region and Kodori gorge.

Other type of operations not envisaged under the plan will also be carried out for the safe and reliable operation of the transmission line.

The performed repair work will significantly increase the stability and the reliability of the operation of the transmission line Kavkasioni (500kV) and the energy system of Georgia.