In October, 2017, during the inspection of the Electric Transmission Line KAVKASIONI (500 kV) there was detected the fact of washing up the gourd surface as a result of heavy rain on the territory adjacent to the two foundations of the N9 middle basis of P2 type. There was a threat of falling down the basis.
Correspondingly, special activities were designed and carried out to resolve the mentioned problem. After working out a plan and acquirement of the required materials the foundations of N9 middle basis were strengthened. The restoration process was launched on November 5, 2017 and over on November 29, 2017. The performed operations maintained the reliability and safety of the power lines.
The restoration work was designed and implemented by JSC SAKRUSENERGO.