In coordination with the National Dispatch center of Georgia, electricity transmission line IMERETI (500kV) was announced under repair from March 15 to 25, 2024.

Repair-maintenance work will be performed on the line in accordance with the business plan 2024 defined by JSC UES SAKRUSENERGO. The repair process includes the following work: the replacement of the damaged and broken insulators, line accessories, repair of conductors, etc. Other type of operations not envisaged under the plan will also be carried out for the safe and reliable operation of the transmission line.

 During the period of IMERETI being under repair, the progress of the works was coordinated and monitored by Mr. Andro Tskhadadze. Mr. Felix Janashia, the head of the labor safety service, and Mr. Demur Buadze, deputy head of the same unit, supervised the safety production of works by the staff. Mr. Guram Javshanashvili, deputy heads of the transportation service, ensured smooth operation of transport and special equipment.