Restoration work on the 500 kV KAVKASIONI transmission line

At the end of January of the current year, conductor damage was detected on the section of the 500 kV KAVKASIONI transmission line passing through the Kodori Valley, specifically in the span between towers No. 184 and No. 185. In particular, one conductor of the middle phase in this span had broken and was hanging down, buried in the snow.

Due to heavy snowfall and weather conditions, access to carry out restoration works was only possible on February 22, 2024. JSC SAKRUSENERGO dispatched Iuri Nadiradze, Head of the Design and Construction Service, and Tengiz Mikava, foreman of the Tsalenjikha Transmission Maintenance Unit. They were joined by specialists from SAKRUSENERGO and “Chernomorenergo” residing in Gali and the Kodori Valley.

The works were carried out under extreme conditions, in an environment of deep snow and freezing temperatures. Despite the unfavorable working conditions, the restoration works were completed within a short timeframe and with high quality.

Other news

ლოგო-1-1200x857-2-qw31cbgkq2fy8i4erku8k3du5unuj5rgxx5ldl8rds

General Meeting of Shareholders of JSC SAKRUSENERGO

599941953_1506206891042148_1064853551260512251_n

Energy Policy of Georgia

571201403_1460351892294315_8062422109977194013_n

Silk Road Forum