Restoration work on the 500 kV KAVKASIONI transmission line

At the end of January of the current year, conductor damage was detected on the section of the 500 kV KAVKASIONI transmission line passing through the Kodori Valley, specifically in the span between towers No. 184 and No. 185. In particular, one conductor of the middle phase in this span had broken and was hanging down, buried in the snow.

Due to heavy snowfall and weather conditions, access to carry out restoration works was only possible on February 22, 2024. JSC SAKRUSENERGO dispatched Iuri Nadiradze, Head of the Design and Construction Service, and Tengiz Mikava, foreman of the Tsalenjikha Transmission Maintenance Unit. They were joined by specialists from SAKRUSENERGO and “Chernomorenergo” residing in Gali and the Kodori Valley.

The works were carried out under extreme conditions, in an environment of deep snow and freezing temperatures. Despite the unfavorable working conditions, the restoration works were completed within a short timeframe and with high quality.

Other news

ლოგო-1-1200x857-2-qw31cbgkq2fy8i4erku8k3du5unuj5rgxx5ldl8rds

30Th anniversary of JSC UES SAKRUSENERGO

ლოგო-1-1200x857-2-qw31cbgkq2fy8i4erku8k3du5unuj5rgxx5ldl8rds

ინფორმაცია სს გეს საქრუსენერგოში თანამდებობების დასაკავებლად ჩატარებული ღია კონკურსის შედეგების შესახებ

710098523_1648318786830957_7918535884546678721_n

JSC UES SAKRUSENERGO celebrated Georgia’s Independence Day in Telavi